Tag: Res Judicata

First District Holds that Claims that Could Have Been Raised in Prior Litigation Are Barred by the Doctrine of Res Judicata

In Atwell v. City of Rohnert Park (2018) 27 Cal.App.5th 692,  the First District Court of Appeal upheld a lower court’s ruling in favor of the respondent city on a motion for judgment on the pleadings, finding that petitioner’s claims were barred by the doctrine of res judicata. The First District’s opinion, not originally slated for publication, held that subsequent individual petitioners were in privity with the Sierra Club in a prior suit, that the same claim of inconsistency with the general plan could have been raised in that prior suit, and the public interest exemption to the doctrine of res judicata did not apply in the circumstances of the instant case.

In 2010, the city certified an EIR and related approvals for Walmart to expand an existing store to include a 24-hour supermarket. The city found that the project was consistent with its General Plan’s Policy LU-7, concerning land use for grocery stores. Sierra Club filed suit in 2012 under the California Environmental Quality Act (CEQA) and the state Planning and Zoning law (“Sierra Club action”). While Sierra Club raised the general plan consistency issue in its initial pleading, it did not argue it in its briefing. The court in the Sierra Club action consequently did not address the issue in its decision invalidating the EIR.

The city prepared a revised EIR in 2015, but it did not alter the consistency analysis involving Policy LU-7. The city subsequently reapproved the project. In its 2015 findings, the city stated that the project was even more consistent with Policy LU-7 than before, as it would serve several neighborhoods that were now coming online in the store’s vicinity. Petitioners in the instant action, who had not participated in the prior Sierra Club action, filed this suit. The city successfully moved for a judgement on the pleadings, and this appeal followed.

Following a final judgment on the merits, the doctrine of res judicata bars a party, and persons in privity with that party, from relitigating a claim that was actually litigated or that could have been litigated in the prior action. At issue is whether the current petitioners are in privity with Sierra Club, and if the general plan consistency claim was litigated in the prior action.

The court concluded that the two petitions raised the same general issue, as both alleged inconsistencies with the same general plan policy. The court considered it irrelevant that Sierra Club did not argue this issue in its briefing, even though it raised it, as res judicata extends to claims that could have been litigated, even if they weren’t.

In reaching this decision, the court dismissed the petitioners’ argument that the claims were different because they challenged the newer 2015 findings. For purposes of res judicata, plaintiffs have suffered the same injury when the same primary right is at stake, even if there are different theories of recovery, different forms of relief sought, or if there are new facts supporting recovery. The court distinguished the instant case from other decisions in the land use and CEQA context, where the second suit was a factually-distinct attempt to comply with CEQA and concerned distinct episodes of noncompliance. That was not the case here. Even though the city’s 2015 resolutions were “new” and revisions were made to other sections of the EIR as a result of the Sierra Club action, the court decided that the later petition did not raise concerns about those revisions, and those revisions were unrelated to Policy LU-7.

The court found that the instant and previous parties were in privity, even though the later petitioners were unaffiliated with Sierra Club, did not otherwise coordinate with or collaborate with the Sierra Club, did not participate in the prior suit, and were seeking redress for both public and private harms.

A nonparty is in privity with a prior party if they have an interest so similar to that party’s interest that the party acted as the nonparty’s virtual representative in the first action, such that the nonparty can reasonably expect to be bound by the prior decision. The actual relationship between the parties is not the key question, but rather, those entities’ relationship to the subject matter of the litigation.

Here, both appellants’ petition and the prior petition alleged claims as members of the public and harms that would be suffered by the community. The petitioners failed to distinguish the harms that they would suffer, directly or indirectly, from the harms alleged in the Sierra Club action, nor could the court find meaningful distinction.

The petitioners were adequately represented in the prior suit, even though Sierra Club ultimately decided not to pursue the general plan consistency claim. Lack of adequate representation has been found when the prior petitioner abnegated its role as a public agent, committed a procedural error that prejudiced the outcome, or lacked the funding to pursue the claim. There was no such evidence in this case. The court therefore assumed that the Sierra Club diligently litigated their petition, and made an informed decision not to pursue the consistency argument. The current petitioners were bound by this tactical decision.

The court rejected the petitioners’ argument under the public policy exception. The public policy exception holds that when the issue is a question of law rather than of fact, the prior determination is not conclusive either if injustice would result or if the public interest requires that relitigation not be foreclosed. The petitioners argued that they raised a unique and important issue of statutory construction. But this situation was not a question of law regarding statutory interpretation. Rather, at issue was the interpretation of an ordinance as applied to a project approval. Such a claim inherently requires the court to consider the facts and circumstances surrounding the project, and not just questions of law.

Finally, the court stated that even if the claims were not barred by res judicata, the city’s finding of consistency was not arbitrary and capricious. The city had discretion to interpret its own policies, and could determine that the project would meet that policy’s goal of creating neighborhood-serving supermarkets.

Third District Finds Trial Court Committed Non-Prejudicial Error When It Excluded Documents from Record Under the Deliberative Process Privilege, Upholds Revised EIR Against Other CEQA Challenges

Citizens for Open Government v. City of Lodi, (3rd Dist. March 28, 2012 [modified April 25th, 2012]) __Cal.App.4th__ (Case No. C065463, C065719)

Factual and Procedural Background

In 2002, Browman Company applied to the City of Lodi for a use permit to develop a 35-acre shopping center. In 2003, the city issued a NOP for a draft EIR for the proposed project. The city approved the project in 2004. Lodi First and Citizens for Open Government (COG) filed separate lawsuits (Lodi First I and Citizens I) challenging the project.

In December 2005, the trial court granted the petition for writ of mandate in Lodi First I.  The city council rescinded approval of the project and decertified the 2004 EIR. In 2006, the city issued a NOP for the revised EIR. In 2007, COG and the city stipulated to dismiss Citizens I.

In October 2007, the city circulated revisions to the EIR for public review and comment.  The city concluded some of the comments it had received on the revised draft EIR were beyond the scope of the revisions and barred by res judicata. The city declined to provide substantive responses to these comments. In May 2009, the city council conditionally approved the project entitlements and adopted findings of fact and a statement of overriding considerations for the project.

In order to proceed with the project, the city filed a petition to discharge the writ in Lodi First I. As part of this process, the city lodged a supplemental administrative record. Both COG and Lodi First filed separate lawsuits challenging the final revised EIR. After filing their lawsuits, both groups contended the supplemental administrative record excluded documents, including internal agency communications and communications with city consultants.

COG filed a motion to augment the supplemental administrative record. The court granted the motion in part and denied the motion in part based on the attorney-client, attorney-work-product and deliberative process privileges. In 2010, following a hearing on the merits, the trial court granted the City’s request to discharge the 2005 writ in Lodi First I and deny the petitions in Citizens II and Lodi First II. Both Lodi First and COG appealed.

The Appellate Court’s Decision

On appeal, Lodi First and COG argued the trial court erred in applying the deliberative process privilege to exclude some emails from the administrative record. Appellants also challenged the sufficiency of the revised EIR on numerous grounds and disputed the trial court’s ruling precluding them from challenging certain issues based on res judicata.

The Deliberative Process Privilege

Under the deliberative process privilege, senior officials in government enjoy a qualified, limited privilege not to disclose certain materials or communications. These include the mental processes by which a given decision was reached and other discussions, deliberations, etc., by which government policy is processed and formulated. The deliberative process showing must be made by the one claiming the privilege. Not every deliberative process communication is protected by the privilege.  Instead, the privilege is implicated only if the public interest in nondisclosure clearly outweighs the public interest in disclosure.

In the trial court, the city argued the deliberative process privilege applied because the city manager, city attorney, community development director, and other consultants engaged in various deliberative discussions and document exchanges concerning revisions to the EIR. The privilege was required, the city argued, “to foster candid dialogue and a testing and challenging of the approaches to be taken…” On appeal, Lodi First claimed this assertion was insufficient to support nondisclosure through the deliberative process privilege. The appellate court agreed, finding the city offered a correct statement of policy, but that invoking policy was not sufficient to explain the public’s specific interest in nondisclosure of the documents at issue. As a result, the city failed to carry its burden, and the trial court erred in excluding 22 e-mails from the administrative record based on the deliberative process privilege.

While the trial court erred in excluding these documents, this error was not necessarily prejudicial. Under the standard for prejudicial error established by the California Constitution, the appellant bears the burden to show it is reasonably probable he or she would have received a more favorable result at trial had the error not occurred.

Lodi First acknowledged it could not satisfy its burden to prove prejudice on appeal because it had not seen the documents that were erroneously withheld. Lodi First claimed the improper withholding of the documents itself was prejudicial because it was impossible for Lodi First to acquire them. The appellate court disagreed and noted Lodi First should have sought writ review of the trial court’s ruling on the motion to augment the administrative record. In addition, the appellate court, citing Madera Oversight Coalition Inc. v. County of Madera (2011) 199 Cal.App.4th 48, disagreed with Lodi First’s contention that the incomplete record itself was a prejudicial error requiring reversal regardless of the actual contents of the withheld documents.

The Range of Alternatives Considered

Lodi First argued the revised EIR did not comply with CEQA because the range of alternatives to the project did not both satisfy most of the project objectives and reduce significant effects of the project. Relying on both the CEQA Guidelines and long-standing precedent, the court rejected Lodi First’s argument.

First, the court of appeal cited CEQA Guidelines section 15126.6 for the assertion that “there is no ironclad rule governing the nature or scope of the alternatives to be discussed other than the rule of reason.” In addition the court noted that the California Supreme Court has explained how a “rule of reason” must be applied to the assessment of alternatives to proposed projects.

In this case, the revised project considered five alternatives: (1) no project; (2) alternative land uses; (3) reduced density; (4) reduced project size; and (5) alternative project location.  The alternative land use and reduced project density alternatives were not considered for further evaluation because they were infeasible or would not meet the goals of the project. The appellate court found the rejection of these alternatives for further review was reasonable.  The three remaining alternatives were discussed in detail in the revised EIR and provided substantial evidence of a reasonable range of alternatives.

Urban Decay Analysis

The trial court granted the petition for writ of mandate in Lodi First I, in part, because the analysis of cumulative urban decay impacts was inadequate for omitting two related projects in the geographic area. An updated economic impact/urban decay analysis was prepared in response to the trial court’s order to decertify the original EIR.

Lodi First argued the revised EIR inaccurately described the project’s environmental setting by failing to discuss existing blight and decay conditions in east Lodi. The appellate court, by de novo review, determined the blight at issue was not necessarily related to the retail environment at all. Further, the revised EIR analyzed the potential for urban decay with consideration of conditions in east Lodi. The revised EIR’s discussion of cumulative urban decay impacts was adequate under CEQA.

The Economic Baseline

COG argued the city erred in the revised EIR by failing to assess urban decay impacts “under radically changed economic conditions.” COG asserted the city should have reassessed urban decay impacts in light of the economic recession that occurred after the 2006/2007 economic analysis performed for the project. The appellate court determined the city’s decision not to update the baseline was supported by substantial evidence. First, the city offered evidence that updating the baseline presented a “moving target” problem, where updates to the analysis would not be able to keep pace with changing events.  In addition, the city presented evidence that the changing economic conditions did not affect the urban decay findings based on the 2006/2007 economic analysis. Therefore, the city did not abuse its discretion when it declined to update the baseline.

Agricultural Impacts

COG argued the original EIR and revised EIR failed to disclose cumulative impacts to agriculture and that there was no substantial evidence to support the rejection of a heightened mitigation ratio.

The appellate court first determined that the revised EIR satisfied the standards established by the CEQA Guidelines for discussing cumulative impacts. The EIR explained the amount of prime farmland lost due to the project, the amount of land lost due to the project and other proposed projects, and that the cumulative impacts to agricultural resources would be significant and unavoidable. The discussion met the standard for “adequacy, completeness, and a good faith effort at full disclosure.”

After finding the revised EIR’s discussion of cumulative impacts to agricultural resources adequate, the appellate court determined the city did not have to accept a heightened mitigation ratio as asserted by COG. The city required a 1:1 conservation easement ratio for the loss of farmland, but also determined that agricultural easements do not completely mitigate for the loss of farmland. The city adopted a statement of overriding considerations and asserted the 1:1 ratio is appropriate for the project. COG argued the rejection of a 2:1 mitigation ratio was not supported by substantial evidence. The appellate court disagreed and noted that the appropriate standard was whether the finding that there were no feasible mitigation measures to reduce the impacts to prime farmland was supported by substantial evidence.

The Doctrine of Res Judicata

Lodi First attempted to argue the revised EIR failed to disclose cumulative water supply impacts. The trial court held that res judicata barred Lodi Frist from raising this claim. The appellate court agreed.

Res Judicata (claim preclusion) bars relitigation of a cause of action that was previously adjudicated in another proceeding between the same parties or parties in privity with them and that adjudication resulted in a final decision on the merits. In this case, a writ was issued in Lodi First I and was final on the merits.  The trial court granted Lodi First’s petition and held the 2005 EIR was inadequate under CEQA. The city chose not to appeal, and the ruling was final because the time to appeal passed.

Lodi first attempted to argue res judicata did not preclude its water supply challenge because it was based on new information and the city’s 2009 findings regarding the project’s water supply impacts differed from its 2005 findings. For the purposes of res judicata, causes of action are considered the same if based on the same primary right. A claim is based on the same primary right if based on the same conditions and facts in existence when the original action was filed.

The appellate court determined the problem of overdraft cited by Lodi First was not new evidence. The city’s own 1990 general plan identified overdraft in the aquifer. While Lodi First claimed new evidence established more information than the 1990 EIR, the critical fact was that the city’s water supply was inadequate to serve new development.  This was known at the time of the 2004 EIR. In addition, the court determined the findings were consistent in that both findings were that the project would have no significant impact on water supply and therefore, no mitigation was necessary

Finally, the appellate court disagreed with Lodi First that res judicata should not be applied to the water supply issue due to public policy. When the issue is a question of law rather than of fact, res judicata may not apply if injustice would result or if the public interest requires that relitigation be allowed. Lodi First’s water supply issue did not present a question of law, so the public interest exception did not apply.

Conclusion

This case demonstrates the limitations of the deliberative process privilege for public agencies. Agencies attempting to rely on this privilege must be prepared to support their assertion of the privilege with a specific showing that the nondisclosure outweighs the public interest in disclosure; broad policy statements are not enough to support application of the privilege.  In addition, the case offers an important reminder of the consequences of failing to raise all potential arguments in original CEQA proceedings, and indeed, most regular civil proceedings.

RMM partners Andrea Leisy and Howard Wilkins and associate Laura Harris represented real party in in interest Browman Development in this litigation.

Second District Holds the Purpose of CEQA Is to Consider Impacts of Projects on the Environment rather than Environment’s Impacts on the Project

Ballona Wetlands Land Trust v. City of Los Angeles
(2011) 201 Cal.App.4th 455

The Second District Court of Appeal upheld a revised EIR for the Playa Vista phase two project, prepared after a previous peremptory writ had been issued. The project opponents challenged the revised EIR with respect to the project description, the analysis of archaeological resources, the analysis of sea level rise resulting from global climate change, and the finding of no significant impact on land use consistency. The court concluded that the EIR adequately discussed preservation in place of archaeological resources and sea level rise. The court also concluded that newly-asserted challenges to the project description and the findings on consistency were beyond the trial court’s jurisdiction in these proceedings after issuance of the peremptory writ.

CEQA Guidelines section 15126.4, subdivision (b)(3) states that preservation in place is the preferred manner to mitigate impacts on historic archaeological resources and expressly requires a discussion of preservation in place in an EIR involving a historical archaeological site. The revised EIR stated that preservation in place is the preferred manner of mitigating impacts to archaeological sites, but explained the infeasibility of preservation in place. The revised EIR therefore concluded that data recovery and curation are appropriate mitigation measures, and described other mitigation measures that had already occurred and that would continue to occur. The court held that this analysis satisfied the requirements of CEQA Guidelines section 15126.4, subdivision (b)(3).

The court then addressed whether the revised EIR was required to analyze the effects of sea level rise on the project. The court explained that “the purpose of an EIR is to identify the significant effects of a project on the environment, not the significant effects of the environment on the project.” In doing so, the court cited CEQA Guidelines section 15126.2, subdivision (a), which states in part that: “The EIR shall also analyze any significant environmental effects the project might cause by bringing development and people into the area affected. For example, an EIR on a subdivision astride an active fault line should identify as a significant effect the seismic hazard to future occupants of the subdivision. The subdivision would have the effect of attracting people to the location and exposing them to the hazards found there. Similarly, the EIR should evaluate any potentially significant impacts of locating development in other areas susceptible to hazardous conditions (e.g., floodplains, coastlines, wildfire risk areas) as identified in authoritative hazard maps, risk assessments or in land use plans addressing such hazards.”

The court explained: “We believe that identifying the environmental effects of attracting development and people to an area is consistent with CEQA’s legislative purpose and statutory requirements, but identifying the effects on the project and its users of locating the project in a particular environmental setting is neither consistent with CEQA’s legislative purpose nor required by the CEQA statutes.” The court thus held that “[c]ontrary to Guidelines section 15162.2 subdivision (a). . . an EIR need not identify or analyze such effects.”

Regarding sea level rise, the revised EIR briefly noted that global warming could result in sea level rise and the inundation of coastal areas, but provided no specific analysis of the impact on the phase two project site. It also explained in responses to comments that according to estimates by the Intergovernmental Panel on Climate Change that the project was not expected to be subjected to inundation as a result of sea level rise resulting from climate change. The court had rejected the opponents request for judicial notice of a flood hazard map prepared by the city prior to approval of the project because the map was not included in the administrative record and the opponents had shown no extraordinary circumstances to justify consideration of the extra-record evidence. The court held the revised EIR’s discussion of sea level rise was adequate.

In previous litigation, the court had held that the previous EIR’s analysis of land use impacts was inadequate, and therefore a peremptory writ was issued. In their challenge to the return to the writ and in their supplemental petition challenging the revised EIR, the project opponents asserted new challenges related to the project description, land use impacts, and the city’s findings regarding these issues. The court held that these challenges had to be raised prior to the judgment in the previous round of litigation, and therefore rejected them.