In Communities For A Better Environment v. Bay Area Air Quality Management District (2016) 1 Cal.App.5th 715, the First District Court of Appeal held a petition for writ of mandate as time-barred under Public Resources Code § 21167, subdivision (d). Petitioners argued that the ”discovery rule” should apply because the Bay Area Air Quality Management District (“District”) failed to provide public notice of the ministerial approval and the project itself (a change in operation at a transloading facility from ethanol to crude oil) was “hidden from the public eye.” The court held that the statute governed when the public was deemed to have constructive notice of a project, and the discovery rule postpones the accrual of an action beyond the date of the injury, not beyond the date when the plaintiff is deemed to have constructive notice.
The District issued a ministerial permit for the project in July 2013, which was not subject to CEQA. But the District did not file the optional notice of exemption (“NOE”) and the applicant began transloading crude oil at its facility in October 2013. The conditions of the permit were modified in October and December of 2013, and the District issued a second permit incorporating these modifications in February 2014. On March 27, 2014 petitioners filed a petition for a writ of mandate. The District argued that the petition was time-barred because it should have been brought within 180 days of July 2013, when the permit was issued. Petitioners argued that they only became aware of the project on July 31, 2014, and that the facility is completely enclosed making the change in operation “invisible.” The trial court dismissed the petition without leave to amend as time-barred under 21167.
The First District Court of Appeal distinguished Concerned Citizens of Costa Mesa, Inc. v. 32nd Dist. Agricultural Assn. (1986) 42 Cal.3d 929 (“Concerned Citizens”). In Concerned Citizens, the Court interpreted “the date of commencement of the project” to mean “commencement” of the project approved by the lead agency and analyzed in the EIR. Because the project had changed significantly, the petitioners could bring an action within 180 days of when they knew or reasonably should have known that the project commenced was substantially different from the approved project. Here, petitioners did not argue that there was a substantial change in the project, and instead argued that the discovery rule should postpone the accrual of the action until they had actual notice of the project. The First District found this argument to have been rejected in Concerned Citizens, as contrary to legislative intent.
The Court of Appeal also distinguished Ventura Foothill Neighbors v. County of Ventura (2014) 232 Cal.App.4th 429 (“Ventura Foothills”). In that case, the height of a planned building was changed from 75 feet to 90 feet, and while a notice of determination (“NOD”) was filed because of the change, the NOD did not disclose the change in height. The court in Ventura Foothills determined that the 30-day statute of limitations for NODs only applied to the determinations announced in the NOD. Since the change in height was not disclosed, the 30-day statute had not run. Here, the petitioners could not point to any deficiencies in a required notice.
The court stated that in both cases the court interpreted the statute so that the triggering date for barring an action did not occur. Because petitioners could not argue for such an interpretation in this case, their claim was time-barred. Similarly, they could not amend their pleadings to show that the dates of constructive notice in 21167 had not occurred more than 180 days prior to their filing suit.